Veteran's Parkway Phase III - Construction Timeline

 

Will County is in the process of beginning the Veterans Parkway Phase III Project. This project consists of the reconstruction and widening of the roadway, the installation of a four-way traffic signal at Luther and Schmidt Road, redirecting Luther Drive to tie in with Dalhart where another four-way traffic signal will be installed. In conjunction with this project, the Village of Romeoville will be installing landscaped islands, burying the utility lines, and resurfacing and opening Naperville Drive. As they near project completion, a vinyl fence will be installed along the new Veteran’s Parkway and Naperville Drive.

Click here for a map (pdf) of Veteran's Parkway.

Total Completion Date for the Veteran’s Parkway Project June 2010


The Tentative Project Schedule

Veterans Parkway Phase III Tentative Project Schedule

September

  • Construction contract awarded

October

  • Various utility companies begin facility relocation process
  • Construction contracts executed
  • Preconstruction conference held
  • General contractor construction schedule submitted for review

November

  • Utility relocation work continues
  • Drainage and utility operations commence (dependent upon general contractor construction schedule)
  • Earthwork and grading operations commence (dependent upon general contractor construction schedule)
  • Comcast cable expects to have facility relocation work completed

December

  • Utility relocation work continues
  • AT&T expects to have facility relocation work completed
  • Various underground and earthwork operations continue

January

  • Utility relocation work continues
  • Nicor Gas expects to have facility relocation work completed
  • Various underground and earthwork operations continue

February

  • Utility relocation work continues

March

  • Commonwealth Edison expects to have facility relocation work completed
  • Barring inclement weather the general contractor may begin project



 

 
 
 

 


 
 
 

 



For more information or if you have questions please contact Dawn Caldwell at (815) 886-7200 ext 418.